2025 Chip and Seal Street Project
Project title: 2025 Chip Seal Street Project
Project purpose or justification:
The 2025 Streets Project is designed to maintain and enhance the quality, safety, and longevity of Buena Vista’s transportation infrastructure. This includes chipseal, slurry seal, and paving work across multiple streets and parking areas. The project supports the Town's commitment to effective roadway maintenance, improving driving surfaces, reducing future repair costs, and ensuring reliable transportation access for residents and visitors.
Project objective:
Perform chipseal and slurry seal treatment on designated streets and parking lots to extend pavement life.
Conduct milling and paving on Marquette Avenue to maintain roadway quality and usability.
Award contracts through a competitive bid process to ensure cost-effective and high-quality services.
Complete the project within specified timelines to avoid disruption and minimize inconvenience to the public.
Project scope:
The project includes:
Chipseal and Slurry Seal Treatment on: (A-1 Chipseal Company)
Brookdale Avenue
Waters Avenue
Antero Circle
Isobel Court
Monarch Court
East Main Street
Town Hall East parking lot
Railroad Street parking lot
Milling and Paving on: (Pavement Maintenance Services, Inc.)
Marquette Avenue
Project Deliverables:
Completed chipseal and slurry seal on all specified streets and parking lots.
Completed milling and paving of Marquette Avenue.
Compliance with project specifications, timelines, and contract terms.
Two-year warranty period on work completed, with final acceptance after this period.
Documentation and certifications including:
Notice of Award
Performance and Payment Bonds
Agreement Documents
Final Payment Notice upon project completion and acceptance
Project stakeholders:
Owner: Town of Buena Vista, CO
Engineer: Town Engineer, Buena Vista
Contractors:
A-1 Chipseal Company (Chipseal and Slurry Seal)
Pavement Maintenance Services, Inc. (Paving on Marquette Avenue)
Board of Trustees: Approves contracts and oversees fiscal responsibility
Public Works Department: Project management, bid process, and oversight
Community Members: End-users benefiting from improved infrastructure
Project timeline:
Notice to Proceed: Upon contract execution
Substantial Completion: Within 60 calendar days after Notice to Proceed
Final Completion: Within 75 calendar days after Notice to Proceed
Liquidated Damages: $300 per day for failure to meet completion deadlines
Final Acceptance: Two years following initial acceptance, contingent on warranty compliance
- The Chip Seal Project will have 75 days from the contract start date.
- The chip sealing should only affect one lane at a time, and there are no anticipated road closures, however the contractors will have flags and control traffic as needed.
| Component | Amount |
|---|---|
| Chipseal, Crackseal & Slurry Seal (A-1 Chipseal Company) | $127,809.40 |
| Paving (Marquette Ave, Pavement Maintenance Services, Inc.) | $143,368.75 |
| Total Project Cost | $271,178.15 |
| Funding Source: | 2025 Adopted Budget - Street Fund Capital Projects |
| Budget Allocations: | - Chip Seal: $180,000 - Crack Seal: $20,000 - Street Paving/Overlay: $300,000 |
Project title: 2025 Chip Seal Street Project
Project purpose or justification:
The 2025 Streets Project is designed to maintain and enhance the quality, safety, and longevity of Buena Vista’s transportation infrastructure. This includes chipseal, slurry seal, and paving work across multiple streets and parking areas. The project supports the Town's commitment to effective roadway maintenance, improving driving surfaces, reducing future repair costs, and ensuring reliable transportation access for residents and visitors.
Project objective:
Perform chipseal and slurry seal treatment on designated streets and parking lots to extend pavement life.
Conduct milling and paving on Marquette Avenue to maintain roadway quality and usability.
Award contracts through a competitive bid process to ensure cost-effective and high-quality services.
Complete the project within specified timelines to avoid disruption and minimize inconvenience to the public.
Project scope:
The project includes:
Chipseal and Slurry Seal Treatment on: (A-1 Chipseal Company)
Brookdale Avenue
Waters Avenue
Antero Circle
Isobel Court
Monarch Court
East Main Street
Town Hall East parking lot
Railroad Street parking lot
Milling and Paving on: (Pavement Maintenance Services, Inc.)
Marquette Avenue
Project Deliverables:
Completed chipseal and slurry seal on all specified streets and parking lots.
Completed milling and paving of Marquette Avenue.
Compliance with project specifications, timelines, and contract terms.
Two-year warranty period on work completed, with final acceptance after this period.
Documentation and certifications including:
Notice of Award
Performance and Payment Bonds
Agreement Documents
Final Payment Notice upon project completion and acceptance
Project stakeholders:
Owner: Town of Buena Vista, CO
Engineer: Town Engineer, Buena Vista
Contractors:
A-1 Chipseal Company (Chipseal and Slurry Seal)
Pavement Maintenance Services, Inc. (Paving on Marquette Avenue)
Board of Trustees: Approves contracts and oversees fiscal responsibility
Public Works Department: Project management, bid process, and oversight
Community Members: End-users benefiting from improved infrastructure
Project timeline:
Notice to Proceed: Upon contract execution
Substantial Completion: Within 60 calendar days after Notice to Proceed
Final Completion: Within 75 calendar days after Notice to Proceed
Liquidated Damages: $300 per day for failure to meet completion deadlines
Final Acceptance: Two years following initial acceptance, contingent on warranty compliance
- The Chip Seal Project will have 75 days from the contract start date.
- The chip sealing should only affect one lane at a time, and there are no anticipated road closures, however the contractors will have flags and control traffic as needed.
| Component | Amount |
|---|---|
| Chipseal, Crackseal & Slurry Seal (A-1 Chipseal Company) | $127,809.40 |
| Paving (Marquette Ave, Pavement Maintenance Services, Inc.) | $143,368.75 |
| Total Project Cost | $271,178.15 |
| Funding Source: | 2025 Adopted Budget - Street Fund Capital Projects |
| Budget Allocations: | - Chip Seal: $180,000 - Crack Seal: $20,000 - Street Paving/Overlay: $300,000 |
-
π£οΈ Heads Up, Buena Vista! Road Work Coming This Week
Share π£οΈ Heads Up, Buena Vista! Road Work Coming This Week on Facebook Share π£οΈ Heads Up, Buena Vista! Road Work Coming This Week on Twitter Share π£οΈ Heads Up, Buena Vista! Road Work Coming This Week on Linkedin Email π£οΈ Heads Up, Buena Vista! Road Work Coming This Week linkThe Town of Buena Vista Public Works Department is kicking off crackseal operations as part of our ongoing 2026 Streets Chipseal Projectβhelping extend the life of our roads and keep travel smooth and safe.
π Where Youβll See Activity
Crews will be working with rolling single-lane closures in the following areas:
- Meadow Lane
- South San Juan Avenue
- West Main Street
- Cedar Street
- South Main Neighborhood
π When to Expect Impacts
- Start: Wednesday, April 22 at 8:00 AM
- End: Friday, April 24 (end of day)
- Weather may impact timing
π§ What to Expect
- Rolling single-lane closures with flaggers
- Short travel delays as crews move through neighborhoods
- Active work zones throughout the day
The Town will implement a traffic control plan to maintain safe and steady traffic flow during the project.
π« Important: No On-Street Parking
To ensure crews can fully complete the work:
- Please do not park on affected streets
- Avoid parking along edges of asphalt and paved areas
This helps crews seal all surfaces efficiently and avoid delays.
π¬ Stay Informed
Have questions or want to learn more about Town projects?
π Visit my-bv.com
π Call Public Works: 719-395-6898π Thank You, Buena Vista!
We appreciate your patience as we invest in safer, longer-lasting streets for our community.
The Town of Buena Vista Public Works Department is kicking off crackseal operations as part of our ongoing 2026 Streets Chipseal Projectβhelping extend the life of our roads and keep travel smooth and safe.
π Where Youβll See Activity
Crews will be working with rolling single-lane closures in the following areas:
- Meadow Lane
- South San Juan Avenue
- West Main Street
- Cedar Street
- South Main Neighborhood
π When to Expect Impacts
- Start: Wednesday, April 22 at 8:00 AM
- End: Friday, April 24 (end of day)
- Weather may impact timing
π§ What to Expect
- Rolling single-lane closures with flaggers
- Short travel delays as crews move through neighborhoods
- Active work zones throughout the day
The Town will implement a traffic control plan to maintain safe and steady traffic flow during the project.
π« Important: No On-Street Parking
To ensure crews can fully complete the work:
- Please do not park on affected streets
- Avoid parking along edges of asphalt and paved areas
This helps crews seal all surfaces efficiently and avoid delays.
π¬ Stay Informed
Have questions or want to learn more about Town projects?
π Visit my-bv.com
π Call Public Works: 719-395-6898π Thank You, Buena Vista!
We appreciate your patience as we invest in safer, longer-lasting streets for our community.
-
Travel Impact β Marquette Avenue and South Railroad Street Pedestrian Trail
Share Travel Impact β Marquette Avenue and South Railroad Street Pedestrian Trail on Facebook Share Travel Impact β Marquette Avenue and South Railroad Street Pedestrian Trail on Twitter Share Travel Impact β Marquette Avenue and South Railroad Street Pedestrian Trail on Linkedin Email Travel Impact β Marquette Avenue and South Railroad Street Pedestrian Trail link
Travel Impact β Marquette Avenue and South Railroad Street Pedestrian Trail
The Town of Buena Vista Public Works Department, as part of its responsibility to ensure public health and safety, is notifying the public that there will be a full road and trail closure for the paving portion of the 2025 Paving Project. Area maps are included below.
The Town of Buena Vista Streets Department is responsible for overseeing the project, and reports that the milling and paving process of the street and trail will begin on Wednesday, August 13th starting at 7:00AM and will be completed by the end of day, Friday, August 15th.
Local traffic will be impacted, and full street closure on Marquette Avenue with a detour via South Railroad Street and Baylor Drive will be in place during most of this project. Marquette Avenue will be open each evening to traffic. Rough roads with loose gravel are anticipated prior to final paving. On-street parking is prohibited in these locations at these times.

The South Railroad Street Pedestrian Trail will be closed to pedestrians during the project.

Every effort will be made to ensure smooth traffic flow and clear communication throughout the duration of this project. A traffic control plan will be implemented with full road and trail closures, as well as single lane closures with flaggers. These operations are a part of the 2025 Streets Paving project.
If you have any questions or would like to know more about the 2025 Streets Projects, check out my-bv.com or please contact the Town of Buena Vista Public Works at 719-395-6898.
Travel Impact β Marquette Avenue and South Railroad Street Pedestrian Trail
The Town of Buena Vista Public Works Department, as part of its responsibility to ensure public health and safety, is notifying the public that there will be a full road and trail closure for the paving portion of the 2025 Paving Project. Area maps are included below.
The Town of Buena Vista Streets Department is responsible for overseeing the project, and reports that the milling and paving process of the street and trail will begin on Wednesday, August 13th starting at 7:00AM and will be completed by the end of day, Friday, August 15th.
Local traffic will be impacted, and full street closure on Marquette Avenue with a detour via South Railroad Street and Baylor Drive will be in place during most of this project. Marquette Avenue will be open each evening to traffic. Rough roads with loose gravel are anticipated prior to final paving. On-street parking is prohibited in these locations at these times.

The South Railroad Street Pedestrian Trail will be closed to pedestrians during the project.

Every effort will be made to ensure smooth traffic flow and clear communication throughout the duration of this project. A traffic control plan will be implemented with full road and trail closures, as well as single lane closures with flaggers. These operations are a part of the 2025 Streets Paving project.
If you have any questions or would like to know more about the 2025 Streets Projects, check out my-bv.com or please contact the Town of Buena Vista Public Works at 719-395-6898.
-
Travel Impact β Antero Circle including Monarch Court and Isabel Court; Waters Avenue and Brookdale Avenue 8/9 & 8/11
Share Travel Impact β Antero Circle including Monarch Court and Isabel Court; Waters Avenue and Brookdale Avenue 8/9 & 8/11 on Facebook Share Travel Impact β Antero Circle including Monarch Court and Isabel Court; Waters Avenue and Brookdale Avenue 8/9 & 8/11 on Twitter Share Travel Impact β Antero Circle including Monarch Court and Isabel Court; Waters Avenue and Brookdale Avenue 8/9 & 8/11 on Linkedin Email Travel Impact β Antero Circle including Monarch Court and Isabel Court; Waters Avenue and Brookdale Avenue 8/9 & 8/11 link
The Town of Buena Vista Public Works Department, as part of its responsibility to ensure public health and safety, is notifying the public that there will be rolling single lane closures along Antero Circle including Monarch Court and Isabel Court; Waters Avenue to Brookdale Avenue. This travel impact will be in place to complete chipseal operations.


The Town of Buena Vista Streets Department is the department responsible for overseeing the work, and reports that the chipping process will begin on Saturday, August 9th starting at 7:00AM and the chip material application will be completed by the end of the same day. Loose gravel is anticipated prior to cleanup. The cleanup and completion of the project will be the following Monday, August 11th starting at 7:00AM. On street parking is prohibited in these locations at these times. Local traffic will be impacted, and a rolling single lane closure will be in place while the work is being completed.
Every effort will be made to ensure smooth traffic flow and clear communication throughout the duration of this project. A traffic control plan will be implemented using flaggers and a rolling single lane closure. These operations are a part of the 2025 Streets Paving project.
If you have any questions, please contact the Town of Buena Vista Public Works at 719-395-6898.
To stay informed on this project, please register and follow the 2025 Chip Seal Project Page
The Town of Buena Vista Public Works Department, as part of its responsibility to ensure public health and safety, is notifying the public that there will be rolling single lane closures along Antero Circle including Monarch Court and Isabel Court; Waters Avenue to Brookdale Avenue. This travel impact will be in place to complete chipseal operations.


The Town of Buena Vista Streets Department is the department responsible for overseeing the work, and reports that the chipping process will begin on Saturday, August 9th starting at 7:00AM and the chip material application will be completed by the end of the same day. Loose gravel is anticipated prior to cleanup. The cleanup and completion of the project will be the following Monday, August 11th starting at 7:00AM. On street parking is prohibited in these locations at these times. Local traffic will be impacted, and a rolling single lane closure will be in place while the work is being completed.
Every effort will be made to ensure smooth traffic flow and clear communication throughout the duration of this project. A traffic control plan will be implemented using flaggers and a rolling single lane closure. These operations are a part of the 2025 Streets Paving project.
If you have any questions, please contact the Town of Buena Vista Public Works at 719-395-6898.
To stay informed on this project, please register and follow the 2025 Chip Seal Project Page
-
Travel and Parking Impact β East Main Street, Railroad Street Parking Lots, and Railroad Right-of-Way
Share Travel and Parking Impact β East Main Street, Railroad Street Parking Lots, and Railroad Right-of-Way on Facebook Share Travel and Parking Impact β East Main Street, Railroad Street Parking Lots, and Railroad Right-of-Way on Twitter Share Travel and Parking Impact β East Main Street, Railroad Street Parking Lots, and Railroad Right-of-Way on Linkedin Email Travel and Parking Impact β East Main Street, Railroad Street Parking Lots, and Railroad Right-of-Way link
The Town of Buena Vista Public Works Department, as part of its responsibility to ensure public health and safety, is notifying the public that there will be full street and parking lot closures on July 29, 2025. This travel impact will be in place to complete slurryseal operations.
The Town of Buena Vista Streets Department is the department responsible for overseeing the work, and reports that this work is planned to start on Tuesday, July 29 at 7:00AM and closed streets and parking lots will be opened by approximately 7:00PM. Local traffic will be impacted, and full road closures will be on East Main Street from Highway 24 N to the Railroad Street intersections as well as a portion of the
Railroad Right-of-Way at Town Hall. Both the North Railroad Street and South Railroad Street parking lots will also be closed during this period. Cars that remain parked in these locations will be towed starting at 6:00AM on Tuesday, July 29, 2025.

Every effort will be made to minimize the congestion and confusion created by this project. A CDOT approved traffic control plan will be implemented. These operations are a part of the 2025 Streets Paving project and this portion of the project is to maintain the paved surfaces of East Main Street and both Railroad Street Parking lots. If you have any questions, please contact the Town of Buena Vista Public Works at 719-395-6898.
The Town of Buena Vista Public Works Department, as part of its responsibility to ensure public health and safety, is notifying the public that there will be full street and parking lot closures on July 29, 2025. This travel impact will be in place to complete slurryseal operations.
The Town of Buena Vista Streets Department is the department responsible for overseeing the work, and reports that this work is planned to start on Tuesday, July 29 at 7:00AM and closed streets and parking lots will be opened by approximately 7:00PM. Local traffic will be impacted, and full road closures will be on East Main Street from Highway 24 N to the Railroad Street intersections as well as a portion of the
Railroad Right-of-Way at Town Hall. Both the North Railroad Street and South Railroad Street parking lots will also be closed during this period. Cars that remain parked in these locations will be towed starting at 6:00AM on Tuesday, July 29, 2025.

Every effort will be made to minimize the congestion and confusion created by this project. A CDOT approved traffic control plan will be implemented. These operations are a part of the 2025 Streets Paving project and this portion of the project is to maintain the paved surfaces of East Main Street and both Railroad Street Parking lots. If you have any questions, please contact the Town of Buena Vista Public Works at 719-395-6898.
-
Update: Travel Impact South Railroad Street 7/28 to 7/29
Share Update: Travel Impact South Railroad Street 7/28 to 7/29 on Facebook Share Update: Travel Impact South Railroad Street 7/28 to 7/29 on Twitter Share Update: Travel Impact South Railroad Street 7/28 to 7/29 on Linkedin Email Update: Travel Impact South Railroad Street 7/28 to 7/29 link
Road closure postponed to July 28 - 29:
Travel Impact β South Railroad Street Water Line Replacement
The Town of Buena Vista Public Works Department, as part of its responsibility to ensure public health and safety, is notifying the public that there will be road closure for a water line replacement on South Railroad Street at 533 South Railroad Street.
The Town of Buena Vista Water Department, the department responsible for replacing the line, reports that this work is expected to start Monday, July 28, 2025, and is expected to be completed by the end of the day, Tuesday, July 29, 2025. Local traffic will be impacted, and a full road closure adjacent to 533 South Railroad will be executed at 7:00AM and will be closed to through traffic. Detour signage will route traffic through Cedar Street on the north side and Marquette Avenue on the south side of the closure. Residents on South Railroad Street will still have access, only through traffic will be blocked.
Every effort will be made to minimize the congestion and confusion created by this project. A traffic control plan will be implemented using signage and barricades to easily identify the closure and work zone. The focus of this project is to support the on-going stewardship of the Townβs water resources and maintain the integrity of our public infrastructure.
If you have any questions, please contact the Town of Buena Vista Public Works at 719-395-6898.
Road closure postponed to July 28 - 29:
Travel Impact β South Railroad Street Water Line Replacement
The Town of Buena Vista Public Works Department, as part of its responsibility to ensure public health and safety, is notifying the public that there will be road closure for a water line replacement on South Railroad Street at 533 South Railroad Street.
The Town of Buena Vista Water Department, the department responsible for replacing the line, reports that this work is expected to start Monday, July 28, 2025, and is expected to be completed by the end of the day, Tuesday, July 29, 2025. Local traffic will be impacted, and a full road closure adjacent to 533 South Railroad will be executed at 7:00AM and will be closed to through traffic. Detour signage will route traffic through Cedar Street on the north side and Marquette Avenue on the south side of the closure. Residents on South Railroad Street will still have access, only through traffic will be blocked.
Every effort will be made to minimize the congestion and confusion created by this project. A traffic control plan will be implemented using signage and barricades to easily identify the closure and work zone. The focus of this project is to support the on-going stewardship of the Townβs water resources and maintain the integrity of our public infrastructure.
If you have any questions, please contact the Town of Buena Vista Public Works at 719-395-6898.
Who's Listening
-
SW
Phone 719-581-1049 Email bvpwdir@buenavistaco.gov -
TO
Phone 719-581-1045 Email towens@buenavistaco.gov -
MW
Phone (719) 581-1047 Email mwarriner@buenavistaco.gov
Lifecycle
-
Open
2025 Chip and Seal Street Project has finished this stageThis consultation is open for contributions.
-
Under Review
2025 Chip and Seal Street Project is currently at this stageContributions to this consultation are closed for evaluation and review. The project team will report back on key outcomes.
-
Final report
this is an upcoming stage for 2025 Chip and Seal Street ProjectThe final outcomes of the consultation are documented here. This may include a summary of all contributions collected as well as recommendations for future action.