2025 Chip and Seal Street Project

Project title: 2025 Chip Seal Street Project
Project purpose or justification:
The 2025 Streets Project is designed to maintain and enhance the quality, safety, and longevity of Buena Vista’s transportation infrastructure. This includes chipseal, slurry seal, and paving work across multiple streets and parking areas. The project supports the Town's commitment to effective roadway maintenance, improving driving surfaces, reducing future repair costs, and ensuring reliable transportation access for residents and visitors.
Project objective:
Perform chipseal and slurry seal treatment on designated streets and parking lots to extend pavement life.
Conduct milling and paving on Marquette Avenue to maintain roadway quality and usability.
Award contracts through a competitive bid process to ensure cost-effective and high-quality services.
Complete the project within specified timelines to avoid disruption and minimize inconvenience to the public.
Project scope:
The project includes:
Chipseal and Slurry Seal Treatment on: (A-1 Chipseal Company)
Brookdale Avenue
Waters Avenue
Antero Circle
Isobel Court
Monarch Court
East Main Street
Town Hall East parking lot
Railroad Street parking lot
Milling and Paving on: (Pavement Maintenance Services, Inc.)
Marquette Avenue
Project Deliverables:
Completed chipseal and slurry seal on all specified streets and parking lots.
Completed milling and paving of Marquette Avenue.
Compliance with project specifications, timelines, and contract terms.
Two-year warranty period on work completed, with final acceptance after this period.
Documentation and certifications including:
Notice of Award
Performance and Payment Bonds
Agreement Documents
Final Payment Notice upon project completion and acceptance
Project stakeholders:
Owner: Town of Buena Vista, CO
Engineer: Town Engineer, Buena Vista
Contractors:
A-1 Chipseal Company (Chipseal and Slurry Seal)
Pavement Maintenance Services, Inc. (Paving on Marquette Avenue)
Board of Trustees: Approves contracts and oversees fiscal responsibility
Public Works Department: Project management, bid process, and oversight
Community Members: End-users benefiting from improved infrastructure
Project timeline:
Notice to Proceed: Upon contract execution
Substantial Completion: Within 60 calendar days after Notice to Proceed
Final Completion: Within 75 calendar days after Notice to Proceed
Liquidated Damages: $300 per day for failure to meet completion deadlines
Final Acceptance: Two years following initial acceptance, contingent on warranty compliance
- The Chip Seal Project will have 75 days from the contract start date.
- The chip sealing should only affect one lane at a time, and there are no anticipated road closures, however the contractors will have flags and control traffic as needed.
Component | Amount |
---|---|
Chipseal, Crackseal & Slurry Seal (A-1 Chipseal Company) | $127,809.40 |
Paving (Marquette Ave, Pavement Maintenance Services, Inc.) | $143,368.75 |
Total Project Cost | $271,178.15 |
Funding Source: | 2025 Adopted Budget - Street Fund Capital Projects |
Budget Allocations: | - Chip Seal: $180,000 - Crack Seal: $20,000 - Street Paving/Overlay: $300,000 |