April 19 2024

Notice to Award

May 06 2024

Contract Start Date

May 13 2024

Crack Seal Process Begins

June 13 2024

Chip Seal Process Begins (Tentative)

The Town of Buena Vista Public Works has scheduled chip-seal to be installed on the following streets;


 Windwalker Road

 Dreamcatcher Road

 Shaman Way

 Connie Drive

 South Sangre De Cristo Ave

 Merrill Lane

 Railroad ROW (between Main Street and East Arkansas)


Anticipated installation start date is June 13th , 2024


Please be advised these streets will be closed during the time of installation.

For more information, please contact the Town of Buena Vista Public Works Department


719 395 6898


Please be advised these streets will be closed during the time of installation.

For more information, please contact the Town of Buena Vista Public Works Department


719 395 6898

July 08 2024

End Date: ( Tentative 75 Days from Notice to Proceed)

End Date: (75 Days from Notice to Proceed)