2024 Paving Project
Project title: 2024 Paving Project
Project purpose or justification: Many streets within the town need milled and paved. These are degraded asphalt streets.
Project objective: To install asphalt applications to existing Town of Buena Vista streets.
Project scope: The existing street with be milled and serviced with an asphalt application, compliant with CDOT SX mix of Town streets. The streets selected for this year’s paving projects are:
- County Road 319/Aviation Road
- South Pleasant Avenue
Project deliverables:
- The works includes full depth milling, 3” asphalt overlay compliant with CDOT SX mix and Chip Sealing of various roads at various locations around Town.
- Milling
- Grading
- Repaving
Project stakeholders:
- S & S Unlimited
- Town of Buena Vista Residents
Project timeline:
- Monday/Tuesday 6-24/6-25 to start and the full milling scope is expected to take two days.
- There will be grading work to follow.
- Paving Scope TBD
- Completed by August 16, 2024
Project title: 2024 Paving Project
Project purpose or justification: Many streets within the town need milled and paved. These are degraded asphalt streets.
Project objective: To install asphalt applications to existing Town of Buena Vista streets.
Project scope: The existing street with be milled and serviced with an asphalt application, compliant with CDOT SX mix of Town streets. The streets selected for this year’s paving projects are:
- County Road 319/Aviation Road
- South Pleasant Avenue
Project deliverables:
- The works includes full depth milling, 3” asphalt overlay compliant with CDOT SX mix and Chip Sealing of various roads at various locations around Town.
- Milling
- Grading
- Repaving
Project stakeholders:
- S & S Unlimited
- Town of Buena Vista Residents
Project timeline:
- Monday/Tuesday 6-24/6-25 to start and the full milling scope is expected to take two days.
- There will be grading work to follow.
- Paving Scope TBD
- Completed by August 16, 2024
-
Update to Traffic Impacts – County Road 319/Aviation Road, South Pleasant Avenue
Share Update to Traffic Impacts – County Road 319/Aviation Road, South Pleasant Avenue on Facebook Share Update to Traffic Impacts – County Road 319/Aviation Road, South Pleasant Avenue on Twitter Share Update to Traffic Impacts – County Road 319/Aviation Road, South Pleasant Avenue on Linkedin Email Update to Traffic Impacts – County Road 319/Aviation Road, South Pleasant Avenue linkThe Buena Vista Public Works and Streets Departments, as part of their responsibility to ensure public health and safety, is notifying the public that portions of County Road 319/Aviation Road to be closed and traffic impacts to South Pleasant Avenue have been delayed. Originally slated to start Monday, June 24, 2024, beginning at approximately 8:00 AM and lasting until end of day, Friday, June 28th, 2024, milling is tentatively rescheduled to begin Thursday, June 27th, 2024 on County Road 319/Aviation Road. Milling and paving on South Pleasant Avenue may need to be rescheduled for after the Independence Day holiday.
Thank you!
The Buena Vista Public Works and Streets Departments, as part of their responsibility to ensure public health and safety, is notifying the public that portions of County Road 319/Aviation Road to be closed and traffic impacts to South Pleasant Avenue have been delayed. Originally slated to start Monday, June 24, 2024, beginning at approximately 8:00 AM and lasting until end of day, Friday, June 28th, 2024, milling is tentatively rescheduled to begin Thursday, June 27th, 2024 on County Road 319/Aviation Road. Milling and paving on South Pleasant Avenue may need to be rescheduled for after the Independence Day holiday.
Thank you!
-
Monday/Tuesday 6-24/6-25
Share Monday/Tuesday 6-24/6-25 on Facebook Share Monday/Tuesday 6-24/6-25 on Twitter Share Monday/Tuesday 6-24/6-25 on Linkedin Email Monday/Tuesday 6-24/6-25 link
Start date scheduled.
The full milling scope is expected to take two days. There will be grading work to follow.
Traffic Impacts – County Road 319/Aviation Road, South Pleasant Avenue
The Buena Vista Public Works and Streets Departments, as part of their responsibility to ensure public health and safety, is notifying the public that portions of County Road 319/Aviation Road will be closed and traffic impacts to South Pleasant Avenue starting Monday June 24, 2024, beginning at approximately 8:00 AM and lasting until end of day, Friday, June 28th, 2024 as contractors work to mill asphalt in preparation for repaving. There will be a detour in place for County Road 319/Aviation Road and intermittent delays, single lane traffic on South Pleasant Avenue during this activity.
The detour will route drivers that need to access County Road 319/Aviation Road using McCombs Street to McCormick Street to Gregg Drive. Businesses with access via Gregg Circle will continue to do so. The Streets Department is responsible for supervising the project and reporting that the milling could take approximately two full days to complete.
Every effort will be made to minimize congestion and confusion created by this project. The Streets
Department will be on-site to oversee the project and manage traffic control. The focus of this project is to ensure safe driving conditions while completing the 2024 repaving project. For more information on the project, please visit my-bv.com.
If you have any questions, please get in touch with Buena Vista Public Works at 719-395-6898.


Start date scheduled.
The full milling scope is expected to take two days. There will be grading work to follow.
Traffic Impacts – County Road 319/Aviation Road, South Pleasant Avenue
The Buena Vista Public Works and Streets Departments, as part of their responsibility to ensure public health and safety, is notifying the public that portions of County Road 319/Aviation Road will be closed and traffic impacts to South Pleasant Avenue starting Monday June 24, 2024, beginning at approximately 8:00 AM and lasting until end of day, Friday, June 28th, 2024 as contractors work to mill asphalt in preparation for repaving. There will be a detour in place for County Road 319/Aviation Road and intermittent delays, single lane traffic on South Pleasant Avenue during this activity.
The detour will route drivers that need to access County Road 319/Aviation Road using McCombs Street to McCormick Street to Gregg Drive. Businesses with access via Gregg Circle will continue to do so. The Streets Department is responsible for supervising the project and reporting that the milling could take approximately two full days to complete.
Every effort will be made to minimize congestion and confusion created by this project. The Streets
Department will be on-site to oversee the project and manage traffic control. The focus of this project is to ensure safe driving conditions while completing the 2024 repaving project. For more information on the project, please visit my-bv.com.
If you have any questions, please get in touch with Buena Vista Public Works at 719-395-6898.


-
Mid-June Start Date (TBD)
Share Mid-June Start Date (TBD) on Facebook Share Mid-June Start Date (TBD) on Twitter Share Mid-June Start Date (TBD) on Linkedin Email Mid-June Start Date (TBD) linkTown of Buena Vista 2024 Chip-Seal
Projects
The Town of Buena Vista Public Works has scheduled chip-seal to be installed on the following streets;
Windwalker Road
Dreamcatcher Road
Shaman Way
Connie Drive
South Sangre De Cristo Ave
Merrill Lane
Railroad ROW (between Main Street and East Arkansas)
Anticipated installation start date is June 13th , 2024
Please be advised these streets will be closed during the time of installation.
For more information, please contact the Town of Buena Vista Public Works Department
719 395 6898
Town of Buena Vista 2024 Chip-Seal
Projects
The Town of Buena Vista Public Works has scheduled chip-seal to be installed on the following streets;
Windwalker Road
Dreamcatcher Road
Shaman Way
Connie Drive
South Sangre De Cristo Ave
Merrill Lane
Railroad ROW (between Main Street and East Arkansas)
Anticipated installation start date is June 13th , 2024
Please be advised these streets will be closed during the time of installation.
For more information, please contact the Town of Buena Vista Public Works Department
719 395 6898
Who's Listening
-
TO
Phone 719-581-1045 Email towens@buenavistaco.gov -
SW
Phone 719-581-1049 Email bvpwdir@buenavistaco.gov -
MW
Phone (719) 581-1047 Email mwarriner@buenavistaco.gov
Follow Project
Lifecycle
-
Initiation
2024 Paving Project has finished this stage -
Planning
2024 Paving Project has finished this stage -
Execution
2024 Paving Project is currently at this stage -
Monitoring and Controlling
this is an upcoming stage for 2024 Paving Project -
Closure
this is an upcoming stage for 2024 Paving Project