Consultation has concluded
May 5th, 2022 - During their May 4th meeting, the Planning & Zoning Commission voted unanimously to approve the Special Use Permit for ACA Products. Meeting minutes may be found here.
Applicant ACA Products is seeking a Special Use Permit at their property located on the southeast corner of Gregg Drive and Rodeo Road.
Special Use Permit - as required for mining uses in the I-1 zone district
The applicant owns approximately 105 acres on the southeast corner of Gregg Drive and Rodeo Road. They seek to build a berm around the property similar to the existing berm aroundContinue reading
May 5th, 2022 - During their May 4th meeting, the Planning & Zoning Commission voted unanimously to approve the Special Use Permit for ACA Products. Meeting minutes may be found here.
Applicant ACA Products is seeking a Special Use Permit at their property located on the southeast corner of Gregg Drive and Rodeo Road.
Special Use Permit - as required for mining uses in the I-1 zone district
The applicant owns approximately 105 acres on the southeast corner of Gregg Drive and Rodeo Road. They seek to build a berm around the property similar to the existing berm around their existing pit on the North side of Gregg Drive. The applicant seeks to slowly, over the course of many years, expand their pit operation onto the subject property. This is requested as their current pit is reaching its capacity.
Lifecycle
Application Submitted
ACA Products Pit Expansion has finished this stage
The applicant submitted their complete application(s) and paid the corresponding fees.
Staff Review & Referral Agency Comments
ACA Products Pit Expansion has finished this stage
Staff review the application materials, ensure they fully and accurately represent the proposed project, and then send the relevant application materials out to over 20 referral agencies for comment.
These agencies include Sangre de Cristo Electric, Atmos Energy, the Buena Vista School District, and many more parties. Each party is given approximately 3 weeks to review the application and provide comment.
Comments can include things like special considerations from that party's perspective, notes on infrastructure or easements needed for the project, or other questions and concerns for the applicant and staff to consider.
Applicant Comment Response & Resubmittal
ACA Products Pit Expansion has finished this stage
The staff review comments and referral agency comments are compiled and sorted through. If there are items that the applicant needs to address, these comments are sent back to the applicant along with detailed instructions on what to address.
The applicant is now responsible for resubmitting all requested materials that address the comments raised.
No further work will be done on this application while the Town staff await the applicant's resubmittal.
Applicants have 6 months within which to provide a complete response and resubmittal. If they fail to do so in this time frame, their applications will be abandoned and they will need to start over with a fresh application (and fees).
Applicant Resubmittal & Staff Review
ACA Products Pit Expansion has finished this stage
Applicants resubmit complete materials addressing all of the comments provided on their application(s). Staff then works to review the resubmittal and ensure it addresses all comments.
If there are lingering questions or substantive changes to the application, staff will resend the application to referral agencies.
Staff Action & Report
ACA Products Pit Expansion has finished this stage
If the application is considered complete and has addressed all raised concerns and comments, the staff will prepare a written report with recommendations for review by the appropriate decision making body.
The type of application will dictate who that decision making body is:
Town Administrator (minor subdivisions, minor site plans, encroachment permits, administrative adjustments, and more)
Planning & Zoning Commission (special use permits, major site plans, major subdivisions, rezoning, and more)
Board of Trustees (public improvement agreements, major subdivisions, rezoning, annexations, and more)
Planning & Zoning Commission Action
ACA Products Pit Expansion has finished this stage
Planning & Zoning Commissioners will consider the application and staff recommendations and approve, approve with conditions, deny, or recommend any of those actions to the Board of Trustees.
Approved & Archived
ACA Products Pit Expansion is currently at this stage