Bath House Deck Replacement Project

Share Bath House Deck Replacement Project on Facebook Share Bath House Deck Replacement Project on Twitter Share Bath House Deck Replacement Project on Linkedin Email Bath House Deck Replacement Project link

Title: River Park Bathhouse Deck Replacement

Project Purpose
The original wood decking at the River Park Bathhouse, installed over 30 years ago, had reached the end of its useful life. This project aimed to revitalize the area by replacing the aging materials with a more durable and low-maintenance alternative.

Project Scope
Town staff explored a variety of replacement options and materials, prioritizing safety, accessibility, and long-term durability. The project was scheduled for winter and spring—when the bathhouse is closed—to minimize disruption to park visitors.

Project Objective
To improve accessibility and safety for all users by replacing the old deck and railings with a new, easy-to-navigate system that includes ramps and updated handrails.

Project Deliverables

  • Constructed a new concrete deck to replace the old wood structure

  • Replaced aging wooden railings with more durable metal ones

  • Installed two ADA-compliant ramps—one on each side of the building—for improved accessibility

Project Stakeholders

  • Town of Buena Vista

  • BV Parks Department

  • BV Recreation Department

  • Propernick Concrete (Contractor)

Timeline
Project work occurred from March 2025 to April 2025

Budget
The project was budgeted at $60,000, with approximately $40,000 spent to date.

Title: River Park Bathhouse Deck Replacement

Project Purpose
The original wood decking at the River Park Bathhouse, installed over 30 years ago, had reached the end of its useful life. This project aimed to revitalize the area by replacing the aging materials with a more durable and low-maintenance alternative.

Project Scope
Town staff explored a variety of replacement options and materials, prioritizing safety, accessibility, and long-term durability. The project was scheduled for winter and spring—when the bathhouse is closed—to minimize disruption to park visitors.

Project Objective
To improve accessibility and safety for all users by replacing the old deck and railings with a new, easy-to-navigate system that includes ramps and updated handrails.

Project Deliverables

  • Constructed a new concrete deck to replace the old wood structure

  • Replaced aging wooden railings with more durable metal ones

  • Installed two ADA-compliant ramps—one on each side of the building—for improved accessibility

Project Stakeholders

  • Town of Buena Vista

  • BV Parks Department

  • BV Recreation Department

  • Propernick Concrete (Contractor)

Timeline
Project work occurred from March 2025 to April 2025

Budget
The project was budgeted at $60,000, with approximately $40,000 spent to date.