Bath House Deck Replacement Project

Share Bath House Deck Replacement Project on Facebook Share Bath House Deck Replacement Project on Twitter Share Bath House Deck Replacement Project on Linkedin Email Bath House Deck Replacement Project link

Title: River Park Bathhouse Deck Replacement

Project Purpose
The original wood decking at the River Park Bathhouse, installed over 30 years ago, had reached the end of its useful life. This project aimed to revitalize the area by replacing the aging materials with a more durable and low-maintenance alternative.

Project Scope
Town staff explored a variety of replacement options and materials, prioritizing safety, accessibility, and long-term durability. The project was scheduled for winter and spring—when the bathhouse is closed—to minimize disruption to park visitors.

Project Objective
To improve accessibility and safety for all users by replacing the old deck and railings with a new, easy-to-navigate system that includes ramps and updated handrails.

Project Deliverables

  • Constructed a new concrete deck to replace the old wood structure

  • Replaced aging wooden railings with more durable metal ones

  • Installed two ADA-compliant ramps—one on each side of the building—for improved accessibility

Project Stakeholders

  • Town of Buena Vista

  • BV Parks Department

  • BV Recreation Department

  • Propernick Concrete (Contractor)

Timeline
Project work occurred from March 2025 to April 2025

Budget
The project was budgeted at $60,000, with approximately $40,000 spent to date.

Title: River Park Bathhouse Deck Replacement

Project Purpose
The original wood decking at the River Park Bathhouse, installed over 30 years ago, had reached the end of its useful life. This project aimed to revitalize the area by replacing the aging materials with a more durable and low-maintenance alternative.

Project Scope
Town staff explored a variety of replacement options and materials, prioritizing safety, accessibility, and long-term durability. The project was scheduled for winter and spring—when the bathhouse is closed—to minimize disruption to park visitors.

Project Objective
To improve accessibility and safety for all users by replacing the old deck and railings with a new, easy-to-navigate system that includes ramps and updated handrails.

Project Deliverables

  • Constructed a new concrete deck to replace the old wood structure

  • Replaced aging wooden railings with more durable metal ones

  • Installed two ADA-compliant ramps—one on each side of the building—for improved accessibility

Project Stakeholders

  • Town of Buena Vista

  • BV Parks Department

  • BV Recreation Department

  • Propernick Concrete (Contractor)

Timeline
Project work occurred from March 2025 to April 2025

Budget
The project was budgeted at $60,000, with approximately $40,000 spent to date.

Your Voice, Your Impact.

We want to hear from you!

Thank you for visiting our project page. Please take a moment to share your thoughts, ideas, or questions in the Guest Book below. Your input helps shape this project and ensures community voices are part of the conversation.

How to Participate

  • Share a comment, question, or idea
  • Be respectful and constructive — all voices are welcome
  • Keep it relevant to the project topic
  • Comments will be visible to others after moderation

Please Note:
We review all submissions to maintain a safe and respectful space. Personal details (addresses, phone numbers, etc.) will not be published. Offensive, irrelevant, or inappropriate content will not be approved.

You need to be signed in to comment in this Guest Book. Click here to Sign In or Register to get involved
Page last updated: 30 Jun 2025, 02:11 PM